Progression Timeline

  • Phase 1

    ✓ Building committee re-formed

    ✓ Scope/scale of project defined

    ✓ Vision work begins

  • Phase 2

    ✓ Committees formed for prayer, fundraising, and communication

    ✓ Preliminary discussions with the City

    ✓ Pre-design work begins; needs identification, space planning, engage architect

  • Phase 3

    Finance committee formed

    Vision fully defined

    Pro-forma developed

    Phase I fundraising begins

    ✓ Test fitting to theoretical and actual sites by architect

    ✓ Rezoning discussions with the City

  • Phase 4

    Preferred site selected

    Site offer, negotiation, purchase

    Initial planning and feasibility study

    Rezoning application

    Phase II fundraising begins

  • Phase 5

    Project manager engaged

    Engineers, consultants engaged

    Concept design and approvals

    Rezoning enactment

    Detailed design begins

  • Phase 6

    Contractor bidding and selection

    Detailed design completed

    Cost estimating

    Premitting and final design

    Funding commitments

    Pre-construction and procurement

    Site preparation and foundation work

    Phase III fundraising begins

  • Phase 7

    Engage neighbourhood

    Events planning

    Structural and exterior work

    Interior and systems installation

  • Phase 8

    Finishing and commissioning

    Substantial completion

    Fit out

    First service

Why Now?